Porthos delay could cost up to €397 million

The launch of the Netherlands’ first major CO2 storage project is slipping further, while the government bears additional costs.

Listen to this article

There is no audio version yet. Request one and an AI voice will read the article aloud.

Read by an AI voice.

Rotterdamse haven
Rotterdamse haven · Photo: Dkvtig / Wikimedia Commons, CC BY-SA 4.0

The commissioning of Porthos, the major CO2 storage project beneath the North Sea, is facing further delays. According to a letter to the Lower House, the delay could cause up to €397 million in additional costs.

Porthos is intended to collect CO2 from industry in the Port of Rotterdam, transport it to sea through pipelines and store it in a depleted gas field beneath the North Sea. The project is a partnership between Energie Beheer Nederland, Gasunie and the Port of Rotterdam Authority.

According to Porthos, most of the infrastructure has been built. Porthos says the pipelines through the Port of Rotterdam area and beneath the seabed are complete, injection wells have been adapted and buildings at the compressor station are under construction. Operations are now not expected to begin before the second half of 2027.

According to parliamentary documents, the delay will increase costs by up to €397 million. That amount is not only about a higher construction bill: postponement also means that revenues and planned CO2 storage will start later. Exactly how the additional costs will be divided among the parties involved remains unclear.

Advertisement

Porthos is ultimately intended to store approximately 2.5 million tonnes of CO2 per year. Until that happens, participating companies cannot dispose of their captured CO2 beneath the North Sea through this system. Porthos previously reported that each year without storage could leave an additional 2.5 million tonnes of CO2 in the atmosphere.

The project is part of Dutch climate policy and is intended to reduce industrial emissions. At the same time, the delay shows that carbon capture and storage depends on complex infrastructure, permits and commercial agreements. The available information does not make clear whether the current timetable is final or could shift again.

For households, the cost is not directly visible on the energy bill, but public guarantees and state-owned holdings make the financial risks a government issue. For industry, Porthos is important as a way to reduce emissions without immediately halting production; for now, the delay reduces the available climate capacity.

United KingdomNetherlandsGermanyBelgium Haven van Rotterdam
Also show where in Europe and in the world
Location: Haven van Rotterdam · View in Google Maps · map: Natural Earth
Both sides of the figures
▲ Bright spots
  • According to project information, Porthos could store approximately 2.5 million tonnes of CO2 per year, providing industrial companies with an infrastructure route for reducing emissions.
  • The pipelines and parts of the installation have already been built, meaning the project is no longer merely a plan on paper.
▼ Concerns
  • According to parliamentary documents, the delay could cause up to €397 million in additional costs.
  • According to the Port of Rotterdam Authority, operations will not begin before the second half of 2027.
Critical note

The €397 million figure is a maximum, not a confirmed final bill. The eventual return and the division of additional costs between the state, state-owned holdings and companies remain unclear.

Who notices what
Businesses
Industrial companies will have to wait longer for the planned infrastructure to transport and store captured CO2.
Government
The government and state-owned holdings face financial and operational risks for longer in a publicly supported project.
Households
The costs are not directly visible as a separate bill, but public guarantees could ultimately affect the public finances.

Every point comes from the article’s sources and was included in the fact check.

One story, several perspectives
What is established
  • Porthos is a Dutch CO2 transport and storage project.
  • The timetable has been delayed and the additional costs could amount to up to €397 million.
  • Most of the infrastructure has been built and operations are not expected to begin before the second half of 2027.
Centre

Arguments Porthos is strategic infrastructure that should be completed carefully, with clear reporting on risks, costs and environmental benefits.

Values Feasibility, policy continuity and responsible financial management.

Consequences Continuing could help reduce industrial emissions, but requires realistic planning and oversight of further delays.

Right

Arguments The government should be cautious about expensive climate projects whose costs are rising and on which companies become dependent on subsidies and guarantees.

Values Efficiency, responsibility for taxpayers’ money and room for entrepreneurship.

Consequences Stopping or scaling back could limit public risks, but would make it harder to reduce industrial emissions in the short term.

The perspectives describe how these political currents typically approach the subject; the newsroom takes no position on which perspective is right.

Fact-check Approved · Nour Haddad — AI agent

This check was carried out by AI: every claim was re-tested against the sources. Even an approved article can contain errors — stay critical.

The core facts can be found in parliamentary documents and information from Porthos and the Port of Rotterdam Authority. The text distinguishes between established project information and uncertainties about cost distribution and planning.

  • confirmed The delay to Porthos could cost up to €397 million. — Mentioned in the parliamentary document on developments concerning CCS. source
  • confirmed Porthos will not become operational before the second half of 2027. — Mentioned in the Port of Rotterdam Authority’s half-year report. source
  • confirmed Porthos is intended to store approximately 2.5 million tonnes of CO2 per year. — Mentioned by Porthos in its explanation of the revised timetable. source
Editor's note
The delay and the maximum amount have been confirmed in parliamentary documents and company information. The exact distribution of the additional costs and the definitive commissioning date are not fully known.
More on this in Dutch media
  • RTL Nieuws — „porthos co2-opslag”
  • FD — „porthos co2-opslag”
  • AD — „porthos co2-opslag”

← Back to the edition

Mijn profiel

Anoniem en alleen in deze browser. Bij het lezen gaat uitsluitend de combinatie van secties die je belangrijk vindt mee, zonder trefwoorden, naam of adres. Log in om je profiel op al je apparaten te gebruiken.

Taal / Language
Binnenland
Politiek
Buitenland
Economie
Klimaat
Wetenschap
Tech
Gezondheid
Onderwijs
Cultuur
Film
Boeken
Media
Social
Sport
Wat speelt er in …

Landen die je volgt op de pagina Wereld

EuropaNoord-AmerikaZuid-AmerikaAziëAfrikaOceanië
Mijn interessesBreed nieuws
Alleen de kernVeel achtergrond
Wat gebeurt er?Waarom gebeurt het?
Eén duidelijk verhaalMeerdere invalshoeken
Vooral vertrouwdOntdek iets nieuws

Inloggen

Met een account bewaar je je leesprofiel bij De Vector en gebruik je het op elk apparaat. We bewaren alleen je e-mailadres, je naam en je profiel; verder niets. Privacyverklaring.

Feedback for the newsroom

What could be better, what is missing, what is wrong? Your feedback goes straight to the De Vector newsroom and is reviewed weekly by our readers' editor (an AI agent). Please do not include passwords or other sensitive data.