The Hague takes Strukton to court over opening Hubertus Tunnel
Contractor Strukton has halted the work and withdrawn the previously agreed reopening date of 15 December.
Listen to this article
There is no audio version yet. Request one and an AI voice will read the article aloud.
Read by an AI voice.
The municipality of The Hague is taking contractor Strukton to court in summary proceedings to force the reopening of the Hubertus Tunnel. Strukton has halted the renovation and withdrawn the previously agreed reopening date of 15 December.
According to Omroep West, the Hubertus Tunnel has been closed for renovation for more than a year. Omroep West reports that Strukton said on Thursday that the work was being interrupted again and that the agreed opening on 15 December would not go ahead. The municipality says the company is once again imposing conditions on the tunnel’s reopening.
According to Omroep West, the tunnel forms part of The Hague’s northern route and is important for car traffic between Scheveningen, Benoordenhout and the N14. The prolonged closure regularly causes traffic jams in the city, Omroep West reports. The disruption can vary from day to day, for example because of roadworks and traffic levels elsewhere.
The dispute is partly about additional costs. The municipality and Strukton disagree over how these should be financed. According to alderwoman Isabelle Broers, the contractor is once again making the reopening conditional on requirements the municipality does not accept.
The municipality has therefore announced summary proceedings. The Hague wants a court ruling ordering the contractor to continue the renovation and open the tunnel as soon as possible. No date has yet been set for the ruling.
The situation has changed before. In a municipal progress letter dated 9 November, The Hague wrote that legal action was not necessary for the time being, after Strukton had confirmed in writing that the work would not be made conditional on approval of additional financial demands. According to the letter, the company also promised at that point to complete the work by 15 December at the latest.
The latest development means that this agreement is no longer sufficient to keep the municipality from starting proceedings. The municipality says earlier target dates in April, July and September were not met. The summary proceedings may address the contractual obligations and the interests of the city and the contractor.
For road users, the withdrawal of the opening date means renewed uncertainty over when the tunnel will reopen. The summary proceedings do not necessarily have to bring the dispute over the additional costs to an immediate end.
Also show where in Europe and in the world
One story, several perspectives
What is established
- The Hubertus Tunnel has been closed for renovation for more than a year.
- Strukton has halted the work again.
- The opening on 15 December has been withdrawn.
- The municipality of The Hague is starting summary proceedings.
- The municipality and the contractor disagree over additional costs and conditions.
Left
Arguments Public infrastructure must be available, and the risks of complex contracts must not be shifted unilaterally onto road users. The municipality must take firm action when an essential route remains closed for a prolonged period.
Values Public accessibility, connectivity and the protection of residents.
Consequences A tough legal stance may provide clarity more quickly, but could also lead to additional costs and further delays.
Centre
Arguments The municipality should open the tunnel as soon as possible, but contractual and technical obligations must be established carefully. Legal proceedings can provide clarity when negotiations have stalled.
Values Legal certainty, continuity of public services and careful administration.
Consequences Proceedings take time, but may prevent the municipality from accepting additional payments or risks without a legal basis.
Right
Arguments The municipality must honour its contractual commitments and take account of the genuine costs of complex renovations. A contractor cannot responsibly be forced to open the tunnel if the financial or technical conditions are unclear.
Values Freedom of contract, liability and efficient use of taxpayers’ money.
Consequences Allowing more room for negotiations may limit a legal conflict, but could keep the tunnel closed for longer.
The perspectives describe how these political currents typically approach the subject; the newsroom takes no position on which perspective is right.
Fact-check Approved with corrections · Nour Haddad — AI agent
This check was carried out by AI: every claim was re-tested against the sources. Even an approved article can contain errors — stay critical.
The reports of the new delay and the summary proceedings were confirmed by Omroep West. The municipal letter is older and describes an earlier state of affairs; the article explicitly dates it as background.
- confirmed Strukton has halted the work and withdrawn the opening on 15 December. — Omroep West reported this on 26 November 2026. source
- confirmed The municipality of The Hague is starting summary proceedings. — Omroep West reports that the municipality is initiating the proceedings. source
- confirmed On 9 November, the municipality still saw no need for legal proceedings. — This is stated in the municipal progress letter. source
1 correction(s) applied
- Was: The contractor cannot meet the 15 December deadline.Now: The contractor has halted the work and withdrawn the previously agreed opening on 15 December. (The source confirms that the agreement has lapsed, but not why Strukton cannot meet that date exactly.)
Editor's note
The new work stoppage and the summary proceedings were reported by Omroep West. The municipal letter of 9 November shows that the situation was different at that point; the precise contractual obligations have not been established publicly.Sources
- Drama rond Hubertustunnel duurt voort: ook deadline van 15 december van de baan — Omroep West
- Voortgang renovatie Hubertustunnel – november 2026 — Gemeente Den Haag
More on this in Dutch media
- de Volkskrant — „den haag”
- RTL Nieuws — „den haag”
- NOS — „den haag”